08/12/83 HARRY G. ROWE v. DONALD R. MOSS AND EILEEN

August 12, 1983

HARRY G. ROWE, PLAINTIFF-APPELLANT,
v.
DONALD R. MOSS AND EILEEN PRYOR MOSS, DEFENDANTS-RESPONDENTS



From the Circuit Court of Howell County; Civil Appeal; Special Judge Ray Lee Caskey.

Before Maus, P.j., Hogan, Prewitt, JJ.

The opinion of the court was delivered by: Prewitt

Plaintiff, a licensed architect, sought to recover a fee for preparing house plans and specifications for defendants. Defendants' answer stated that plaintiff was not entitled to recover because he was negligent in several particulars in preparing the plans, including failing "to make proper provisions to allow for the placement of a wood-burning furnace in the basement area". Defendants also counterclaimed, seeking damages for this as well as other alleged deficiencies in the plans, contending that plaintiff "prepared plans and specifications which placed the basement in an improper position making it impossible to install a wood-burning furnace to be connected with the existing chimney". Defendants asserted that this failure damaged them because "the house is not as energy efficient and the fair market value of the house is substantially less than the fair market value of the same house with a wood-burning furnace".

The trial court, sitting without a jury, entered judgment in favor of plaintiff on his petition for $1,060, the amount sought. It found for defendants on their counterclaim, finding that plaintiff knew that defendants wanted to install a wood furnace in their basement and plaintiff owed defendants "a duty to inform them that they either had to move their basement or abandon a wood furnace in their plans" and plaintiff breached that duty, resulting in damages to the defendants. Defendants were awarded damages of $4,000, resulting in them being entitled to receive $2,940 from plaintiff. Plaintiff appeals.

We first discuss plaintiff's contention that the trial court erred in determining that he had a duty to inform the defendants that the location of the basement had to be moved or they had to abandon their plans for a wood furnace because that ruling held plaintiff to a higher standard of technical skill in the preparation of building plans and specifications than the reasonable degree of skill which is required of architects. Plaintiff contends that as he located the basement of the house exactly where defendants wished him to locate it and as he did not agree with them to design a heating system, he had no duty to inform them how the heating system should be located or constructed.

Defendants testified that before consulting plaintiff they had decided they wanted a wood-burning furnace in the basement of the house. Defendant Eileen Moss initially contacted plaintiff regarding drawing the plans and said that on her first visit to his office she gave him a brochure describing the wood-burning furnace they wanted. She also informed him they wanted "a small storage basement for the furnace, hot water tank, where we could put the freezer down there and have storage", and told him what rooms they wanted it under. The basement is approximately one-third the size of the floor above it and it was shown on the plans, as defendants wished, under the kitchen, an office area and a bathroom. Defendants selected the location because they thought it was a "logical place" for the basement's location.

All parties testified that there was never any Discussion or other communication between plaintiff and defendants regarding having to change the location of the basement so a wood-burning furnace might be installed. In his file plaintiff had a brochure on a wood-burning furnace and he testified that defendant Eileen Moss "probably did indicate that she wanted to put in a wood furnace in the house." Plaintiff did not supervise the construction. He was at the site where the house was to be once before he prepared his final plans for defendants. Shortly after receiving the final plans from plaintiff, defendants commenced construction of the house.

Dennis Coulter, an operator of a heating and cooling business, testified that when he first went to the building site the basement and foundation had been constructed and there was sheeting on the floor. While there he determined that a wood furnace could not be installed in the house because the flue would have to run horizontally and that is not safe with a wood furnace. He so informed defendants and a propane furnace was installed in the house. Defendants testified that until Coulter came to the construction site theydid not know that they could not have a wood-burning furnace. Eileen Moss testified that she has since learned that the basement should have been centrally located to have lined up with the fireplace flue.

Defendant Donald Moss testified without objection that Coulter told him that a wood furnace could not be installed because there was between 20 and 22 feet from where the furnace would have to be located in the basement to the fireplace flue. He said that Coulter informed him it would not be safe because "a wood furnace had to be within about three feet of the chimney to be functional, that the long horizontal space that smoke had to go would cool and coal tar and creosote settle out and cool out of it and run back into the furnace and cause a fire." Mr. Moss also testified that it was impossible to install a wood-burning furnace after the basement walls and the basement foundation walls were in. He said it would not have been possible to have installed a separate flue and put in a wood heating system without "putting additional footings in to support it. We would have had to go through -- take out the basement floor and put in additional footings."

An architect, testifying as an expert witness for defendants, said that a wood furnace should be close to the flue and that he would have advised defendants that either the basement had to be located below or adjacent to the flues or that they were not going to be able to install a wood-burning furnace there. He said that "the architect should have told them that wood furnaces or the basement needed to be situated such that the wood furnace would be closer to the flues." He stated that it would be an architect's duty to tell defendants that they were either going to have to move the basement or not have a wood-burning furnace.

An architect holds himself out as being skilled in the science of constructing buildings. 6 C.J.S. Architects § 27, p. 490; Annot., Responsibility of one acting as architect for defects or insufficiency of work attributable to plans, 25 A.L.R.2d 1085, 1086 (1952). "In lay person's terms, a property owner tells an architect basically what kind of structure is desired, and the architect takes it from there, designing the specifications which are later used by engineers and builders." Waddington v. Wick, 652 S.W.2d 147, 150 (Mo. App. 1983).

An architect is required to furnish plans prepared with a reasonable degree of technical skill. Stanley Consultants, Inc. v. H. Kalicak Construction Company, 383 F.Supp. 315, 319 (E.D. Mo. 1974). See also, Dysart-Cook Mule Co. v. Reed & Heckenlively, 114 Mo. App.296, 89 S.W. 591 (1905). An architect owes a duty to those employing him essentially the same as that which is owed by any person to another where such persons holds himself out as possessing skill and ability in some special employment. 5 Am.Jur.2d, Architects, § 8, p. 670. The plans drawn by an architect are tested by the ordinary and reasonable skill usually exercised by one in that profession. Annot., supra, 25 A.L.R.2d at 1088.

The evidence is undisputed that defendants informed plaintiff that they wanted a wood-burning furnace. They must have expected him to provide plans where such a furnace could be installed or else they would not have discussed the furnace with him and have given him the brochure about it. They said they were relying on him as a professional to do so. They could expect to receive, not only a set of professionally designed plans, but plans that would achieve their desired house, or to be advised that what they had informed him they wanted would not work without changes. When the client of an architect advises him of construction goals that are incompatible, we believe that the architect, as one skilled in construction, has an obligation to advise the client that both could not be accomplished. This was basically what defendants' expert witness testified to. Of course, the final decision as to the basement's location would be defendants, but after having consulted professional help, they should have been advised of the consequences of leaving the basement where they originally wanted it. They indicated that if they had known they could not have the furnace as the basement was located they would have moved the basement.

If plaintiff had no knowledge regarding the proper location of such a furnace, he should have acquired it or have advised defendants that he was providing no opinion as to its location and was disclaiming any responsibility for whether it could be installed under his plans. Under our review we cannot say that the trial court erred in finding that plaintiff had a duty to inform defendants that they ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.